• Lifting sling is fixed to the column at exact position of lift.
• Guy ropes are fixed to the column before lifting.
• Lifting equipment lifts the structural column vertically and is positioned in the Pedestal
• Anchor bolts nuts should be fixed and tightened
• Guy ropes are tied as shown in the figure
• Column plumb is checked and sling is released using Boom lift or Scissor lift

Braced Column Erection
• Same Procedure is followed for lifting the second column
• The Portal beam is the primary tying member between the two columns. It is lifted using Crane and
   boom lift used for bolting the portal beam.
• The Eave Strut is immediately erected after the erection of second Column.
• Bracing Rods should be lifted and fixed to the adjacent Columns. Hill Side washers are used to tighten the brace rods.
• The same procedure is followed for erection of the columns on the other side of the grid