Our Product Range - PEB Erection

Provide PEB erection on the contractual basis with the help of expert team. We are able to instantly work on your site with the help of our dedicated team member.

Mandatory documents to be maintained at site during project execution.
• A copy of customer order received
• Copy of work order released to erector by STEELFAB
• Erection Methodology duly approved by STEELFAB engineering department & Team Leader
• Resource Plan duly approved by STEELFAB Team Leader
• Project specific safety plan duly approved by the Safety Engineer to be maintained
• Anchor Bolt (AB), General Arrangement (GA), Erection, and Sheeting drawings stamped as “Good for construction /execution” to be present at site always
• Format of Daily Progress Report, Check lists and all QMS/ISO documents should always be maintained
• Name & contact numbers of all Key persons from projects
• Torque table, test certificates, calibration certificates & fitness certificates of all tools & tackles and of measuring instruments like calibrated torque
  wrench tape of length 5M, 15M & 30M, etc. and other moving equipment
• Copy of Workman Compensation Policy, Labor License, & Contractor All Risk (CAR) policy (if required)

Check list before starting the erection

• Always check, center to center distance of girds and bays with reference to AB and diagonal distance of each grid / bays references

• All tool & tackles required for the erection process must be cross checked with erection drawings and to be available at site before starting the work

• Before commencement of erection a hand over report from civil contractor or consultant must be procured

• Ensure that all the material required for completion of a bay is available at site at its respective location on the previous day