Elastothane Xtra
Application Instructions
METHOD OF APPLICATION
SURFACE PREPARATION
1 Cement concrete surface should be free from dust and loose particles.
A loose particle should be removed by washing or blown air.
2 In existing old terraces such as brick-bat-coba or screeds,
the substrate must be checked for its soundness.
3 Damaged or hollow portions, sharp edges, etc.
must be cut and repaired with a polymer-modified screed.
4 Surface cracks must be filled with Kanfill (Acrylic flexible crack filler)
APPLICATIONS
PRIMER APPLICATION: Mix Elastothane Xtra with water in the ratio of 1:1 by volume.
When primer coat is dry apply the first coat of Elastothane Xtra on the entire surface,
provide scrim fabric at junction of vertical and horizontal surfaces after
one coat then apply the second coat. Drying time between coats will be 5-6 hrs.
2 Ensure that the primer and the 3 coats of
Elastothane Xtra totally achieve a minimum thickness
of 1 mm DFT. Allow the system to air cure for 7 days minimum.