Client |
Krishna Bhagya Jal Nigam Limited, Government of Karnataka, India |
Project |
Multipurpose Project belonging to Government of Karnataka.
Serving dual purposes of Irrigation & Hydro Electric Power generation. |
Location |
Remotely located at around 500 kms. North of Bangalore in southern India. |
Period of Completion |
24 months from 1998 to 2000 |
Scope |
Design, Engineering, Fabrication, Supply, Erection, Installation, Testing and Commissioning of 14 nos. of Radial Crest Gates of size 15.00 M (Width) x 15.24 M (Height) with 2nos. Hydraulic Hoists of 115 T Capacity (Each) along with Remote Control, SCADA system and CCTV arrangements for the spillway of Almatti Dam |
Challengers & Achievements |
Installation, Testing & Commissioning of the work was completed in a record time of six months |